Peachtree Creek Greenway Phase II
Peachtree Creek Greenway Phase II
GDOT PI 0016053
Phase II of the Peachtree Creek Greenway will extend the existing trail from the current terminus at North Druid Hills Road southwest to the Fulton County/City of Atlanta limits, where it will connect to a future trail planned by the City of Atlanta.
Status Update (December, 2023)
Project is currently in the right of way acquisition phase.
Baseline Schedule Milestones: Concept approval - completed; Preliminary Field Plan Review - completed; Final Field Plan Review on or before December 2024; Construction Letting on or before June 2025.
Activity Description |
Proposed Date (as of 08/17/23) |
Right-of-Way (ROW) Authorization |
07/11/23 COMPLETE |
Final Plans Complete |
12/17/24 |
Let Contract (Let Date - The advertised date that construction bid proposals will be opened for GDOT projects. The Let Date is generally the end of the Plan Development Process.) |
07/23/25 |