This project will complete the streetscape improvements (typical cross section – see project LT-01 in the North Druid Hills Road Corridor Study (https://www.brookhavenga.gov/publicworks/page/north-druid-hills-road-corridor-study-0)) from Buford Highway to Gail Drive NE along North Druid Hills Road (approximately 2,700 linear feet). This section includes a continuous 5-foot-wide sidewalk on the western side of North Druid Hills Road and a 10-foot-wide multi-use path on the eastern side.  ADA accessible ramps and crosswalk striping where missing will be installed.  Pedestrian scale lighting along with street furniture will be included.  A short section of raised median is proposed just south of the Red Roof Inn driveway.  A pedestrian crossing is proposed for just south of Gail Drive along with a raised island refuge and actuated flashing beacon.

Funding Source: This project is funded by the City’s Special Service District millage rate. 

Status Update (February 9, 2024):  The project is currently in the design phase of development.  The design work is approximately 80% complete and is anticipated to be complete by the summer of 2024

Status Update (November 15, 2023):  The project is currently in the design phase of development.  The design work is approximately 75% complete and is anticipated to be complete by the first quarter of 2024

Status Update (September 11, 2023):  The project is currently in the design phase of development.  The design work is approximately 70% complete and is anticipated to be complete by late fall. 

Status Update (June 20, 2023):  The project is currently in the design phase of development.  The design work is approximately 60% complete and is anticipated to be complete by late summer/early fall. 

Status Update (May 3, 2023):  The project is currently in the design phase of development.  The design work is approximately 50% complete and is anticipated to be complete by late summer/early fall. 

Status Update (March 3, 2023):  The project is currently in the design phase of development.  The design work is approximately 20% complete and is anticipated to be complete by late summer/early fall. 

Engineering Design Firm: Michael Baker International (MBI)