I-85 Pedestrian Bridge

Pedestrian Gateway Bridge over I-85

This project involves the design of a proposed pedestrian bridge over I-85 connecting W Druid Hills Drive and the Emory University
Executive Park Campus to create a safe path for pedestrians as an alternative to walking along North
Druid Hills Rd and to improve access to Phase II of the Peachtree Creek Greenway.

Status Update (February, 2024)

A contract was awarded to Michael Baker International for Engineering & Design services on this project on October 24, 2023.  Notice to Proceed (NTP) was issued on November 17.

Initial survey activity to support project design has been completed.  Upcoming activity includes database preparation, environmental field survey, and initial alternative development.