GDOT Buford Highway Project - Afton Lane to Clairmont Terrace - PI-0009400

Project Map

Updated 2/9/24

Construction Progress:  37.75% Complete

The Georgia Department of Transportation (GDOT) Buford Highway/Afton Lane to Clairmont Terrace Safety Improvement Project.  The improvements to occur along the corridor include: upgrading existing or adding new sidewalks and retrofitting the existing driveway aprons, adding a raised median from Afton Lane to Clairmont Terrace and adding pedestrian refuge islands.  It also includes upgrading handicap ramps to meet ADA standards and adding pedestrian lighting.  In areas where sidewalk doesn't currently exist or is in bad condition, 5' sidewalks will be constructed.  A 2' stamped concrete strip will be added between the curb and sidewalk where possible to move pedestrians further away from the travel lanes.  Header curb or curb and gutter will be replaced where necessary throughout the project.  Existing drainage structures will be retained or raised wherever possible throughout the corridor.

Notice to Proceed:  4/21/2022

Current Completion Date: 3/31/2025

Contractor: E.R. Snell Contractor, Inc.

To find out more information about the current plans for the project, visit GDOT's project website.