2021 Completed Stormwater Projects
Updated 2/16/24
Return to Stormwater and Water Resources Projects Page
The 2021 Completed List of Stormwater Repairs:
- Woodrow Way at Inman Dr.: – Replace CB’s, pipe, HW, and restore slope. Summit. ($95,018). Completed 1/8/21
- Brook Valley Lane: – Replace two failed culverts under road and GDOT 1033 and 1034 catch basins. RESS. ($47,690). Completed 2/5/21.
- 1169/1166 Wild Creek Trail: - Drainage Rehab: Failing bedding/backfill. Rehab pipe and replace catch basins. The Corbett Group. ($34,04). Completed 01/23/21.
- LaVista Park Discharge Weir Rehab: - The rehabilitation of the city drainage system at LaVista Park and Brook Forest Rd. IPR. ($80,000). Completed 3/23/21.
- Star Dr at Sylvan Cir: - A sinkhole had formed due to a corroded (18” CMP pipe failure). Summit. ($85,029). Completed 06/01/21.
- Fernwood Cir Sinkhole: - A 36” CMP under Fernwood Circle had failured. Two JB’s have defects. Summit ($62,340). Completed .
- 1224 Bernadette Lane: - Drainage Rehab: Rehab pipeline and replace catch basins under road. Vortex Companies. ($3,900). Completed 5/7/21.
- 2900 Mabry Ln: – Sinkhole at intersection of CB top and granite curb, behind curb. Some road base missing. Suspect grouting issues. Re-grout interior of CB and fill sink with flowable fill. Optech work order - # 7271. Completed 02/04/21.
- 1191 Daventry Way: – Repairs to collapsing 54” CMP (point and open cut). Optech - WO # 6805. Completed 3/24/21.
- 1384 Ragley Hall: – Sink hole in ROW. Hollow under pavement and S/W. WO 7242. Self- performed repair, OPTECH. New CB tops formed and poured. Flowable fill used to fill voids. New S/W panels poured over sink hole. Completed 4/20/21.
- 1230 Mayfair Ln: - Drainage Rehab. Failing bedding/backfill. Rehab pipe and replace catch basins. Vortex Companies. ($32,985). Completed 5/12/21.
- Bernadette Ln: - (1224) Rehab pipeline and replace catch basins under road. Vortex Companies. ($39,020). Completed 5/12/21.
- Star Dr at Sylvan Cir: -(18” CMP pipe failure) $85,029 Council approved on 10/27/20. Summit. ($75,029). Completed 5/12/21.
- 2391 Cortez Way: – Failing pipe from street to outfall has caused deep and dangerous sinkhole in rear yard. Replace 30” CMP with 30” HP Storm. Replace HW. Add 2 JB’s on slope to reduce slope. Replace CB at street. Restoration. RESS. ($56,050). Complete 6/3/21.
- 3479 StrafIeld Dr: – A linear sinkhole Stratfield Phase III Project site. Pressure grouting started 9/13/21. Completed: 9/18/21
- 1177 & 1169 W Nancy Creek: – 48” CMP culvert replacement and property restoration. RESS. PO 1763 ($601,000). Completed 10/30/21.
- N Fork Nancy Creek Stream Restoration Project: - Murphey Candler Spillway to Nancy Creek. PO 1688 ($278,042.95). Completed 12.31.21.