2023 ADA Accessible Ramp/Sidewalk Repair/Replace

CONCRETE WORKERS REBUILDING AND INSTALLING ACCESSSABILITY RAMPS IN BROOKHAVEN.

A Community Development Block Grant (CDBG) Project

 

 

CGS, LLC has Been Awarded the 2023 ADA Ramp/Sidewalk Repair/Replace Construction Contract.

 

Work to Commence on Monday, January 29, 2024. 

Expected Completion Date: April 1, 2024.

UPDATED: 4/23/24

 

 

** ALL WORK SPECIFIED IN THIS CONTRACT HAS BEEN COMPLETED. **

FINAL INSPECTIONS ARE COMPLETED.

 

**A LIMITED SURPLUS OF GRANT FUNDING IS BEING USED TO CONTINUE REPAIRING/REPLACING RAMPS/SIDEWALKS IDENTIFIED WITHIN THE ESTABLISHED GRANT ZONE.** 

ONCE IDENTIFIED, THESE NEW LOCATIONS SHALL BE POSTED TO THIS WEBSITE.

 

  • SCHEDULE IS WEATHER DEPENDENT (RAIN OR COLD TEMPERATURES).
  • BECAUSE FEDERAL FUNDING IS INVOLVED, WORK FOR THIS PROJECT IS LIMITED TO BROOKHAVEN CITY COUNCIL DISTRICTS 2 and 4.
  • IMPACT TO PEDESTRIAN AND VEHICULAR TRAFFIC SHOULD BE MINIMAL.
  • RAMPS WILL BE REPAIRED, REPLACED, OR NEWLY INSTALLED WHERE NONE EXISTED BEFORE.
  • ONLY THOSE SECTIONS OF SIDEWALKS IDENTIFIED AS BROKEN OR AS TRIP HAZARDS SHALL BE REPLACED.
  • EXISTING SIDEWALK SECTIONS IN GOOD CONDITION SHALL REMAIN INTACT.

QUESTIONS OR CONCERNS? EMAIL BROOKHAVEN CAPITAL PROJECTS MANAGER, DOUGLAS ARMSTRONG: 

douglas.armstrong@brookhavenga.gov

For Specific Details, As to Where and When, Please Refer to the Table Below, to be Updated Weekly.

***PHOTOS AT THE BOTTOM OF THE PAGE DEPICT PROGRESS FROM THE PAST WEEK'S WORK***

 

DAILY SCHEDULE FOR THE WEEK OF MARCH 18, 2024 & 4/01/24
REVISED: 4/02/24
                     
MONDAY: 3/18/24 LOCATION   DESCRIPTION OF WORK COMPLETE
2144 MILLENIUM WAY DEMOLITION OF EXISTING SIDEWALK MOVED
2145 MILLENIUM WAY DEMOLITION OF EXISTING SIDEWALK MOVED
3446 BRIARWOOD RD CONCRETE POUR & FINISH YES
 
TUESDAY: 3/19/24 LOCATION   DESCRIPTION OF WORK COMPLETE
2144 MILLENIUM WAY DEMOLITION  YES
2145 MILLENIUM WAY DEMOLITION YES
     
 
WEDNESDAY: 3/20/24 LOCATION   DESCRIPTION OF WORK COMPLETE
1880/1900 CURTIS DRIVE DEMO/FORM/POUR/FINISH YES
1657 N DRUID HILLS RD DEMOLITION OF EXISTING SIDEWALK MOVED
1800 CURTIS DRIVE DEMOLITION OF EXISTING SIDEWALK MOVED
 
THURSDAY: 3/21/24 LOCATION   DESCRIPTION OF WORK COMPLETE
1657 N DRUID HILLS RD CONCRETE POUR & FINISH MOVED
1880 CURTIS DRIVE INSTALL DWD YES
1975/1966 STERLING OAKS CR INSTALL DWD YES
 
FRIDAY: 3/22/24 LOCATION   DESCRIPTION OF WORK COMPLETE
2144 MILLENIUM WAY FORM/POUR/FINISH YES
2145 MILLENIUM WAY FORM/POUR/FINISH YES
CLEANUP  CLEANUP YES
 
SATURDAY: 3/24/24 1657 N DRUID HILLS RD: DEMO/FORM/POUR/FINISH NEW TP B RAMP YES
 
MONDAY: 3/25/24 LOCATION   DESCRIPTION OF WORK COMPLETE
2144 MILLENIUM WAY REMOVED FORMS & CLEANUP YES
2145 MILLENIUM WAY REMOVED FORMS & CLEANUP YES
1657 N DRUID HILLS RD REMOVED FORMS & CLEANUP YES
 
MONDAY: 4/01/24 LOCATION   DESCRIPTION OF WORK COMPLETE
VARIOUS INSTALL DWDS YES
     
     

 

* DWD: A standardized surface feature built in or applied to walking surfaces or other elements (ramps) to warn of hazards on a circulation path. Usually yellow or red.

 

 

Click any thumbnail image to view a slideshow

3446 BRIARWOOD RD 25 FT OF NEW RAMP AND SIDEWALK POUR 18MAR24
3446 BRIARWOOD RD AT N ENTRANCE TO HILLCREST APTS S SIDE OF DRIVEWAY ENTRANCE 5FTX5FT FINISHED SIDEWALK 18MAR24
3446 BRIARWOOD RD BLDG A 8FTX8FT SIDEWALK FINISHED 18MAR24
3446 BRIARWOOD RD BLDG A 8FTX8FT SIDEWALK SECTION FINISHED 18MAR24
3446 BRIARWOOD RD RAMP AND 25FT OF SIDEWALK PREPPED FOR CONCRETE 18MAR24
3446 NE CORNER OF BRIARWOOD RD AND S DRIVEWAY TO HILLCREST APTS NEW RAMP AND SIDEWALK POUR 18MAR24
3446A BRIARWOOD RD 25 FT OF NEW RAMP AND SIDEWALK POUR 18MAR24
3446 BRIARWOOD RD 24 FT OF CONCRETE SIDEWALK FINISHED 18MAR24
3446 BRIARWOOD RD 24 FT OF SIDEWALK POURED18MAR24
3446 BRIARWOOD RD RAMP AND 25FT OF SIDEWALK PREPPED FOR CONCRETE 18MAR24
3446 BRIARWOOD RD @ S ENTRANCE TO HILLCREST APTS FINISHED RAMP AND 25FTX5FT OF FINISHED SIDEWALK 19MAR24
2144 and 2145 MILLENIUM WAY @ PINECONE LANE FINISHED CONCRETE RAMP and SIDEWALK  IN ISLAND BETWEEN ADDRESSES 20MAR24
2144 MILLENIUM WAY @ PINE CONE LANE CONCRETE POURED 20MAR24
2144 MILLENIUM WAY @ PINE CONE LANE FORMED AND SOIL PREPPED FOR SIDEWALK RAMP CONCRETE 20MAR24
2144 MILLENIUM WAY @ PINE CONE LANE SIDEWALK and RAMP CONCRETE FINISHED 20MAR24
2144 MILLENIUM WAY @ PINE CONE LANE SIDEWALK RAMP BRACING IN PREP FOR CONCRETE 20MAR24
2145 MILLENIUM WAY @ PINECONE LANE FINISHED CONCRETE RAMP and SIDEWALK 20MAR24
FACING 2144 MILLENIUM WAY @ PINECONE LANE FINISHED CONCRETE RAMP 20MAR24
2144 and 2145 MILLENIUM WAY @ PINE CONE LANE FORMS PLACED FOR NEW CONCRETE SIDEWALK IN ISLAND BETWEEN BUILDINGS 20MAR24
2144 MILLENIUM WAY STRIPPING FORMS AND CLEAUP OF WORK 21MAR24
2144-2145 MILLENIUM WAY FINISHED RAMPS AND SIDEWALK IN ISLAND BETWEEN THE TWO ADDRESSES 21MAR24
2144-2145 MILLENIUM WAY FINISHED TY B RAMPS AND SIDEWALK IN ISLAND NEAREST 2145 21MAR24
2144-2145 MILLENIUM WAY IN ISLAND FORMED AND POURED BACH HEADER CURB FOR TP B RAMP 21MAR24
2145 MILLENIUM WAY FINISHED SIDEWALK LEADING TO GATE ENTRANCE TO 2145 21MAR24
2145 MILLENIUM WAY FINISHED TY B RAMP AND SIDEWALK 21MAR24