Briarwood Park Bond Projects
Estimates for projects at Briarwood Park included in the approved Park Bond Referendum are listed below.
Community Center Renovation | $1,500,000 |
Pool Renovation | $1,290,000 |
Community Garden | $370,000 |
Tennis Court Lighting | $290,000 |
Parkwide Multi Use Trail | $283,220 |
Site Grading | $210,000 |
Wood Bridge – NE Trail | $210,000 |
Recreation Center Parking Renovation | $173,295 |
Demolition | $112,000 |
Erosion and Sediment | $86,850 |
Community Center – Sidewalks & Entrance Renovation |
$73,180 |
Outdoor Classroom – SW Trail | $41,250 |
Landscaping | $41,250 |
Site Furnishings | $39,450 |
Final Grading/Clean Up | $19,000 |
Asphalt Striping Near Tennis Courts | $16,150 |
General Conditions & Services | $854,835 |
Contingency (25%) | $1,402,620 |
TOTAL | $7,013,100 |
As of July 24, 2018