Google Fiber Construction in Brookhaven
Updated: April 22nd, 2024
Created: October 6, 2023
The information provided on this page provides details
to residents related to the installation of Google Fiber
cabling and equipment in Brookhaven's right-of-way.
It is not intended to promote or endorse the services they provide.
GOOGLE FIBER CONSTRUCTION Questions? Call 877-454-6959, Option #3
Contact Google Fiber: Construction Issues Web Form An automated email should acknowledge the report went through and contain a Ticket Number associated with your address.
Google Fiber's Construction Information External Site
Google Fiber's YouTube Construction Video
Google Fiber's Construction Stages FAQ Page
Google is in its construction phase of work, placing the fiber conduits in the ground for their network facilities (mainline underground conduit, handhole boxes, service drops, etc.). They will run under and through virtually every street in the City of Brookhaven.
Click on the list below in “Supporting Documents” for area maps provided by Google Fiber.
The current schedule of work is:
Google Fiber is currently installing new fiber conduit lines in the following locations;
Week 4/7/2024-4/13/2024
ATL106-020 phase 2 - Newbridge Trce, Osborne Rd
ATL106Phase 4 - Briarwood Rd, N Druid, Pine Cone Lane, Buford Hwy(Pending GDOT permit)
ATL106-024 phase 1 - Woodrow Way, Leconte Ave, Inman Dr
ATL106-025 - Victoria St, Cates Ave, Osborne Road
ATL106-202 ROE - Savoy Ln
ATL106-041 - Brookleigh Ln
Week 4/14/2024-4/20/2024
ATL106a Phase 4 N Druid Hills, Briarwood Rd ,Logan Cir
ATL106-026- : Silver Lane Dr, Lynwood Ave, Mendell Cir
ATL106-025 - Antioch Dr, Madison Ave, Georgia Ave
ATL106-028- Kadelston Way, Stratford Dr. Stratfield Cir
ATL106-037 - Harts Mill Rd
ATL106b Phase 1 - Ashford Dunwoody Rd, Harts Mill Rd
Week 4/21/2024-4/27/2024
Phase 4 - Logan Cir, N Druid Hills, Pine Cone Ln, Briarwood Rd
ATL106-025- Mae Ave, Francis St, Antioch Dr.
ATL106-026- Silver Lane Dr, Lynwood Ave, Mendell Cir
ATL106b Phase 1 - Ashford Dunwoody Rd, Harts Mill Rd
Week 4/28/2024-5/4/2024
ATL106-025 - Victoria St, Cates Ave., Osborne Rd
ATL106-026 - Mendell Cir, Osborne Rd, Lynwood Dr
ATL106-020 phase 1- Osborne Rd, Tallulah, Peachtree Rd (SR141)
For Questions or concerns about Google Fiber construction? Call them anytime at the construction Support Line at 877-454-6959, option 3.
- Like any project of this size, the construction process can take some time. We are starting construction now and will work to complete as much of the city as possible through 2023-2024. Google Fiber works to limit disruption and will notify affected residents and businesses as construction is permitted and takes place on their block.
- Will the installation be disruptive to commuter/neighborhood traffic?
- Google Fiber will construct its network within the City right-of-way, per all permitting requirements. The Brookhaven residents can expect to see construction crews in the roadways and adjacent softscapes/yards (area behind the curb that residents generally consider part of their yard) that are part of the City’s right-of-way easement. Crews will notify residents and businesses before construction staging through door hangers, street signage, cones, and other safety and informational efforts.
- Google Fiber works to limit traffic impacts and disruption to residents. Anyone with questions or concerns can contact the Google Fiber Construction hotline at 1-877-454-6959, Option #3.
- Residents can expect a 10-business-day SLA for ticketed construction issues.
BACKGROUND
January 24, 2022 - The Council unanimously approved an ordinance to establish a non-exclusive franchise agreement between the City of Brookhaven and Google Fiber Georgia LLC for the installation of network facilities in the City right-of-way
Completed and Ongoing work for February 2024
Items in Green have been completed
Items in Orange are still in construction